Friday 23 August 2013

[Space reserved for tenuous Wizard of Oz reference]

Most of the wet area tiling is now done, just splash backs left to do where the cornerstone worktops are to be installed (virtually everywhere), the Patio door has now been fixed, but we are still missing a window to the en suite bathroom. And we now have rain water down pipes

The painters have started the internal painting, but so far its limited to removing the doors and doing some surface prep.

The bad news is that over the last week we have received two invoices for Enclosed and fixing stage, which represent about 50% of the build cost, so from this point the interest payments really start clocking up!










No comments: