December/2012 Thought it would be good to build a house
lots of time spend looking at land options and house options
28/01/2013 Appointed Coral to draw up plans
11/02/2013 Land Survey
06/03/2013 Formal finance approval for land purchase
20/03/2013 Receipt of fixed price Contracts
23/03/2013 Signed contracts with Coral, submitted variation for allowance items
02/04/2013 Land purchase
03/04/2013 Lodged application for covenant approval
06/04/2013 Lodged formal application for setback relaxation requested that Coral update plans to move property forward on lot
16/04/2013 Paid 5% deposit
19/04/2013 Formal construction approval received
23/04/2013 Received amended plans
24/04/2013 Covenant approval
26/04/2013 Appointment of Private Certifier
04/05/2013 Tile Selection
10/05/2013 Clipsal Selection
17/05/2013 My Choice
28/05/2013 Council Approval
02/06/2013 All planning and approvals complete and given start date
20/06/2103 Site scraped and temp drive and drainage installed
21/06/2013 Start date
24/06/2013 Piers poured
26/06/2013 Plumbing Installed
03/07/2013 Slab Poured
12/09/2013 Frame Completion
22/07/2013 Roof completed
23/07/2013 Electrical cabling Installed
24/07/2013 Plumbing pipework installed
25/07/2013 Solar system botch install!!!
01/08/2013 Dry lining complete
02/08/2013 Brickwork Complete