The good news is the floor tiling is now done, and it looks a really nice job, we also have kitchen worktops and splash back tiling.
Unfortunately its not all good news, the worktops they have installed in the bathroom are the wrong colour, they are the same wild rocks colour as the Kitchen, however we selected 'Night Sky' (sparkly black), and the worktop in the pantry is missing, probably forgotten!
As the finishing go in we are seeing an increasing number of problems, unfortunately the rate problems are being fixed is falling way behind the rate they are occurring!
Earlier this week we had a letter from coral saying that PC is expected on the 18th September, with handover no earlier than 2nd October, however I'm beginning to have doubts they will make it.
Of course this is exactly the time you want to have a change in site supervisor, especially when a week later our new SS is still claiming he needs to catch up, Im meeting the guy on Monday, and hopefully will start to get some resolution.
Additional Builder tasks
Third party contractor tasks